Kenya Power area · WESTERN REGION
JUMBO MATTRESS, NYAMASARIA
1notices since Mar 2023
6scheduled hours
6havg duration
Friusual day
Complete outage history (1)
| Date | Window | As printed | mapped | Provenance |
|---|
| 2025-05-09 | 09:00-15:00 · 6h | JUMBO MATTRESS, NYAMASARIA | 51% | X post ↗ |
“As printed” preserves Kenya Power’s own wording, including their errors. See the method.