Mathare has had 19 planned interruptions since Mar 2023, below the national rate (0.7×) per resident, and ranks #117 of 257 constituencies by total outage-hours. They usually start around 09:00 on weekdays and last about 7.8 hours. Over the last 12 months the burden rose 38% on the year before.
Planned interruptions
19
since Mar 2023
Outage-hours per 100k
72
0.7× the Kenya average
Last 12 months vs prior 12
+38%
40 h vs 29 h
Typical interruption
7.8 h
most start 09:00, weekdays
Schools in wards touched at least once
304
turn on the Schools layer to see them
Health facilities in wards touched at least once
118
clinics, dispensaries and hospitals
Mathare runs below the national rate (0.7×) per resident, and the burden is rising
Outage-hours per 100,000 residents, monthly · Peak Feb 2024 at 7.7 h per 100k
02468
202420252026
MathareKenya average3-month rolling averageNormalised per 100k so places of different size compare fairly. Method
KCA, Traffic Police HQtrs, Part of Utalii Hotel, Muthaiga Pri Sch, Mathari Teaching Referral Hosp, Muthaiga Police, Muthaiga Golf Club Hotel, Karura Health Centre