Manda-Shivanga has had 3 planned interruptions since Mar 2023, below the national rate (0.4×) per resident, and ranks #799 of 1,113 wards by total outage-hours. They usually start around 08:00 on weekdays and last about 8.2 hours. Over the last 12 months the burden fell 100% on the year before.
Planned interruptions
3
since Mar 2023
Outage-hours per 100k
62
0.4× the Kenya average
Last 12 months vs prior 12
-100%
0 h vs 17 h
Typical interruption
8.2 h
most start 08:00, weekdays
Schools in wards touched at least once
19
turn on the Schools layer to see them
Health facilities in wards touched at least once
0
clinics, dispensaries and hospitals
Manda-Shivanga runs below the national rate (0.4×) per resident, and the burden is easing
Outage-hours per 100,000 residents, monthly · Peak Sep 2025 at 21.5 h per 100k
06.312.518.825
202420252026
Manda-ShivangaKenya average3-month rolling averageNormalised per 100k so places of different size compare fairly. Method
Most interruptions begin 08:00 on a Monday; Sundays are largely spared.